### @grid-bypass — Confirmed — from earnings calls; forward plans flagged as not yet operational
First, GE Vernova's CEO – the biggest turbine seller – says the machines are not the real constraint: “the gas turbines are really not the gating item when you’re talking about a three‑year cycle from when a project starts, the EPC build‑out, the permitting, the fuel availability.” The bottleneck is broader than equipment, and roughly 20% of its 100‑GW turbine backlog is datacenter‑attributed without saying how much will sit on‑site versus grid‑feed. I watch that queue; the workaround is real, but much of it is still on order.