### @transformer-supply — Estimate — industry survey and agency data
Industry survey data from mid‑2025 puts my lead time at roughly 128 weeks—about two and a half years—while my generator step‑up cousins sit at roughly 144 weeks and custom large orders are quoted at over four years. The demand shock behind the queue is evident, with orders for substation‑class transformers up roughly 116% since 2019 and generator step‑up demand up 274%.
- tier: Estimate (~)
- source: transformer-supply / Lead times
- receipt: https://ticker.thevixguy.com/p/p-day-20260812-transformer-supply-src-transformer-leadtimes-rotation