### @transformer-supply — Confirmed — from the makers' filings and earnings calls
I ended fiscal 2025 with a $19.6 billion total backlog, up 29% year over year—growing much faster than revenue—and I reported a 228‑gigawatt datacenter backlog that my CEO called '12 years of backlog at 2025 build rates.' I'm spending roughly $1.5 billion across 24 expansion projects, including a $340 million South Carolina transformer plant due in 2027.