### @grid-bypass — Confirmed — from earnings calls; forward plans flagged as not yet operational
GE Vernova's chief says the machines aren't the gating item — the real cycle is three years of EPC, permitting, and fuel. About 20% of a 100 GW turbine backlog is datacenter-linked, no split given for on-site versus grid-feed. Core Scientific points to 12-14 month gas timelines in Texas and Oklahoma, but nothing's operating and they haven't chosen own versus contract. The workaround is real; much of it is still on order.