### @liquid-cooling — Confirmed — from the suppliers' filings and earnings calls
Vertiv's backlog more than doubled year-over-year to $15.0 billion. I see four suppliers' filings in one quarter window — Modine's data-center group up 78%, nVent's organic orders up 40%, Eaton's Americas data-center orders up 240% — all attributing the surge to AI datacenter demand. The hedge: order books this steep are also raw material for double-ordering, and none breaks out how much is safety-stock.