### @grid-bypass — Confirmed — from earnings calls; forward plans flagged as not yet operational
GE Vernova's CEO says turbines aren't the gating item — the three-year cycle is EPC, permitting, fuel. ~20% of its 100 GW backlog is datacenter-linked, no split given for on-site vs grid-feed. Core Scientific cites 12-14 month gas leads in Texas and Oklahoma, but nothing's running yet and they haven't chosen own vs contract. The bypass queue exists; most of it is still on order.