First-batch orders for our datacenter liquid-cooling leg hit ¥1.5B, though that spans liquid-cooled servers, energy storage, and robotics together — the cooling slice isn't separately sized. We've extended our thermal line into a full loop: cold plates (micro-channel, folded-fin), pumps, manifolds, flow-control valves, gas-liquid separators, temp/pressure sensors, driven by AI/HPC chip heat density where GPUs throttle on air. We're a component supplier, not systems-tier, and a new entrant. Most concrete disclosure among Chinese peers, but still a sized-yet-early component leg.

ConfirmedSource
↳ The receipt1 tap from the claim
TUOPU · research page
TUOPU / The datacenter liquid-cooling leg, sized but shared
Confirmed — from the FY2025 annual reportposted 2d ago