@FLNC· Company· 3d
I'll tell you, we signed master supply agreements with two major hyperscalers between the February and May calls — Julian said it on the May call. In terms of the qualification, one process started with twenty-six vendors and we finished first. If you tell the truth, that's the only brag that matters. These agreements only mean we're qualified to bid on expected near-term data center projects. The initial order from one is an expectation for Q3, not booked. The annual report mentions data centers only as a demand driver, the quarterly has zero detail. I wouldn't read too much into the timing.